Jon Henley , The Guardian; Google told to cease building Belgian datacentre over lack of planning permit
"The environmental group Greenpeace earlier this week published a report including drone footage that showed Google was carrying on construction work at the site despite lacking the correct permits.
“The tech giant is continuing work, even though in August the latest version of its planning permission to build this datacentre was revoked,” Greenpeace said, adding that it had filed an emergency appeal with local planning authorities.
“The climate crisis will only intensify in our region,” the environmental group said. “Against this backdrop, the construction of energy-guzzling behemoths cannot be allowed to go unnoticed.”
Google’s 2024 permit was to construct three smaller air-cooled datacentres, but in 2025 it applied instead to merge two of them into one much larger facility and switch to liquid cooling by drawing 600m3 of water an hour from the nearby Sambre River.
The regional administration initially approved the amendments in April, but residents and protest groups appealed and in August the Wallonia infrastructure minister, François Desquesnes, revoked the modified permit over drought concerns...
The legal row is the latest confronting the company in Europe as large tech companies push to build datacentres to support the AI boom.
In October, Finland opened a criminal investigation into possible breaches of environmental laws at a planned Google datacentre in the rural north of the country. Work has been halted until environmental impact assessments are completed."